Posted on: March 29, 2022

[ARCHIVED] Streetscape

Streetscape Rendering II

Below is a conceptual drawing of the work planned for the Mountain Street area.  Phase2A

Once the project begins, additional information and updates on the progress will be posted here.

April 5, 2022 Update

The City staff along with the streetscape consultants NˑFocus/ViZ, PLLC and the streetscape contractor Greene Building Corporation, held a downtown impacted property/business owner meeting on the evening of April 4th, 2022.  

The main topics were, the expected start date and the phasing of the street and sidewalk closures.   Please see the below for the estimated phasing dates.  The first phase will be the yellow highlighted phase and those closure locations are noted.    All reasonable efforts are being made to lessen the impacts to the businesses and services in these areas.

Streetscape phase 2A_Phasing

If you have a business or service in any of the affected areas and have concerns or wish to be placed on the email notification list; please contact the office of the Assistant City Manager, Nick Hendricks, at 704-730-2125.

April 18, 2022 Update 

Please click the below link to view a detour and public parking access map for the W. Mountain Street closures for Phase 2A of the City's Streetscape plan.

Detour and Public Parking Access Map

April 25,2022 Update

Greene Building Corporation Weekly Contractor Project Progress Update

  • Install Erosion Control Measures - 75% Complete
  • Installed Road Closure Barriers & Cones -100% Complete
  • City of Kings Mountain Removed Existing Benches, Trash Cans & Signage-100% Complete
  • Initial Leak Test Survey for Natural Gas by City of Kings Mountain-100% Complete
  • Conducted Smoke Test, Ran a Camera and Ran Water Through Existing Storm System to Attempt to Confirm Exact Locations of Pipe-100% Complete
  • Located Points for New Catch Basins & Manholes- 100% Complete
  • Started Saw Cutting & Demolition-40% Complete
  • Delivery of Catch Basins & HDPE Pipe-100% Compete

Streetscape_W Mountain St_1

Week 1  Progress Photo

Scheduled for Week of April 25, 2022

  • Continue Phase 1 Demolition
  • Begin Installing New Storm Water Piping


Facebook Twitter Email

Other News in Website News

Document

Job Fair

Posted on: January 20, 2023
Comp Plan 2040

Comprehensive Plan 2040

Posted on: June 7, 2022
water pipes gray with water

Water Projects

Posted on: May 23, 2022
Project South Image

Project South

Posted on: January 13, 2022